Our construction management division just published a ballpark lead time report

21st June, 2012 - Posted by Jeffrey S. Weil, MCR.h, SIOR - No Comments

for various tenant improvement components, such as a 4-8 week lead time for doors, frames and hardware, carpet lead time of 7-8 weeks and server equipment which might require 4-5 weeks … specific locations and circumstances might shorten or lengthen these lead times so this is only a rough guide … Greg Stone’s report can be found at http://officetimes.com/PressReleases/lead_times.html